- Project Information
- Client: Ambatovy Plant Site Tamatave Madagascar
- Date: 2020
- Volume Dredged: 55 000m³
- Material Dredged: thickener overflow with nickel/cobalt/chrome
- Dredger Used: LWT Mudcat Dredger 225 HP
- Dredger Slurry Pump Flow: 400m³ per hour
- Dredging Hours 700
Project overview
Work is continuing for Ambatovy on their CCD Pond with water ph level 2.5(highly corrosive). First stage removal at 25 300m³ of 37 500 with the extension of additional 25 000m³ expected soon.